Case Studies
Underground water supply...
PYBAR harnesses innovative thinking with North Parkes Mines to upgrade the underground water pressure system. The new pressure release valve system has reduced downtime during breakages or maintenance and has created a more accessible means of servicing and maintaining the equipment. Click here to read more |
Small mines back to life...
The high price of gold and copper has initiated an increased interest in redeveloping old deposits that may not previously have made economic sense. PYBAR Mining Services has been instrumental in assisting mines to redevelop old grounds and strike it rich. Click here to read more |
| Moving the earth safely at Cadia Valley Operations |
|
Managing multiple projects safely in environmentally sensitive areas, working in conjunction with client work team, tight deadlines and strict budgets. It's all in a days work for PYBAR's Upper Rods Creek Dam project team at Cadia Valley Operations
PROJECT SCOPE Removal of vegetation and top soil to a clay base on the Upper Rod’s Creek Dam (URCD ), project then extended to dam wall construction. Running concurrently was the new main Cadia access road works projects. Cadia operations required a new dam to be built to ensure its ongoing water supply. This needed to be completed before the traditional rains and forecast wet winter season commenced. Changes in the site layout meant a new main access road was required to be built with a deadline for July 2011. PROCESS Removing vegetation and an average of 1m of top soil, to a clay base to enable the construction of the dam wall. The same team was then engaged to assist the Cadia team to construct the dam wall. Material for the wall was delivered by the pit dump trucks and pushed in using a combination of CVO and PYBAR dozers. At the same time the PYBAR was working on the new main access road, lifting the existing dump bed by 5m before a new liner system could be installed. A fleet of 9 moxy trucks, excavators and road maintenance plant were required to achieve targets. HURDLES Stringent environmental considerations were evident due to an extensive tree clearing at the Eastern end of the proposed wall lift. The team was working on two projects (dam wall & access road works) concurrently, with the success of the project tightly integrated & dependent upon Cadia operations. Significant tonnage was required to be removed within tight timeframes. SOLUTION Three crews were deployed for this project with a 24/7 operation. Considerable site consultation was undertaken with the Cadia team to ensure environmental considerations were adhered to and that the operations continued smoothly and to time, with the complexity of multiple teams (PYBAR and CVO) working on the same project. Additional equipment was re-deployed from PYBAR’s extensive fleet to keep to time and the maintenance & service team was extended to keep the equipment operating at capacity. RESULTS The team received a special mention from the Cadia Environmental team on the professional way the clearing job was undertaken with no direct impact on any endangered or protected wildlife. There were nil non-conformance reports or reworks recorded for the project, it was delivered on target, within budget and above all safely – LTI free.
|

At PYBAR we have strong values, which are embedded into our culture. We believe that these...
PYBAR has secured its first major contract in Tasmania a 12 month cable bolting and 10,000...
PYBAR develops fully self sufficient mobile site office.
Due to planned expansion in these services, PYBAR has several production drilling and...
PYBAR were the Silver sponsor of the 2012 Xstrata Ronald McDonald House North Queensland...
With new, versatile shotcrete equipment, PYBAR has recognised the opportunity and developed our...
See the team in action....
PYBAR's new self sufficient and road registered shotcrete unit, the ultimate in versatility.
A well planned mobilisation, on time handover of portal access and above forecast decline...
A outstanding effort by the Cadia Vallley Operations PYBAR Surface Civil Crews in raising...
PYBAR expands its fleet to over $91.1m, with $6.1m worth of new equipment.
The project involves underground development and production mining of the Hera Deposit located...
Mobilisation has taken place for Saracen's inaugural underground development - the Red October...
PYBAR confirms its position in WA with the Red October development contract.
Equipment & staff from PYBAR has been mobilised to the Xstrata Zinc Lady Loretta project in...
The PYBASH team have recently returned from the 2011 Variety Bash and were successful in raising...
PYBAR announces new project at the Lady Loretta decline project in North Queensland
The bash begins this morning from Baulkham Hills, Sydney (Sat 6 Aug) Thanks to the sponsors who...
Rio Tinto has appointed PYBAR Mining Services to commence the installation of ground support...
Castlemaine Goldfields re-development the Ballarat Gold Mine - progress report on underground...
At a recent photo shoot at PYBAR's Tritton project, the fairer side of the PYBAR team showed...
See one of PYBAR's underground mines at work as ABC goes down to the northern section of the...
The Greens have called for the Mining Super Profits tax to be debated again, and this time Bob...
PYBAR Mining Services has been awarded the tender for development work at Osborne Mine with...
With gold prices now at extraordinary highs PYBAR is helping mines to develop old grounds to...
Significant growth in contracts and projects has seen PYBAR Mining Services break through the...
New equipment trial by PYBAR Mining Services reduces the interruption of oversized rocks in...


